Parent Avenue Infrastructure Renewal Project Tecumseh to Giles

Published Date
Thursday, October 8, 2020

October 8, 2020

Windsor, ON: As part of an ongoing infrastructure renewal program by the Windsor Utilities Commission (WUC), Coco Paving will undertake the following construction project, beginning Tuesday, October 13, 2020, weather permitting:

  • Construction of a new 300mm diameter PVC watermain on Parent Avenue – Tecumseh to Giles

 Please note that traffic will be reduced to one lane in each direction, with on street parking completely eliminated. The project is expected to take approximately 10 weeks to complete.

While every effort will be made to minimize traffic impacts and afford local access to residents, occasional delays can be expected. To ensure the safety of our workers, we request that motorists exercise safety precautions when approaching the construction site.